Key Aspects:
Freyssinet scope of works included design, supply and installation of new access platforms and replacement of spherical bearings.
Freyssinet designed, delivered and executed the works within the time specified by BHP.
Tight timeline allowing 7 days shutdown to jack the bridge by 30mm, remove the existing bearings, demolish the grout pads, replace the 32 new bearings at 7 piers and 2 abutments, recast grout pads under new bearings, cure grout and lower the bridge back to its position.
The bulk of the installation works was done outside the shutdown period. Freyssinet handed the completed bridge back to BHP 24 hours early.